At 30% completion, Highway 105 between 10th Street and South Loop 336 is under reconstruction and widening from two to four lanes. At a cost of $52.35 million, the timeline for the project is now through the third quarter of 2027. It is being funded by the state.
At 5% completion, between FM 830 and FM 1097 in Willis, I-45 is undergoing a northbound ramp reversal. At a cost of $3.17 million, the timeline on the project is now through the second quarter of 2025. It’s state funded.
At 65% completion, Highway 105 is being reconstructed and widened from two to four lanes between South Loop 336 and FM 1484. At a cost of $89.88 million, the timeline on the project is now through the third quarter of 2027. The funding source is federal and state funding.
At 31% completion, in order to widen lanes and restripe intersections, TxDOT is using an existing right of way on Highway 242 between FM 1488 and I-45. At a cost of $29.11 mlllion, the timeline is now through the first quarter of 2026. The funding source is federal and state funding.